Editing openings in walls with multiple construction layers

Opening in walls with multiple construction layers are basically edited in the same way as single-tier walls. Make sure that you edit each construction layer separately. When you select the openings in a single step, the changes you make only apply to the first layer.

The following example, which corresponds to "Moving an opening in a wall of the as-built category", shows how to move a window in a two-tier wall.

To move a window in a two-tier wall of the as-built category

  1. Select the drawing file for the new building elements and open the drawing file with the as-built and demolition data in edit mode.

    Note: Openings are automatically inserted in the associated wall, regardless of whether the drawing file with the wall is current or open in edit mode.

    Start by converting the as-built opening to a demolition object.

  2. Click Conversion for Building Alteration Work.
  3. Click Properties and define the demolition parameters for the as-built opening in one of the following ways:
  4. Draw the new building opening over the demolition opening where you require.

    Each new component automatically gets the New building category.

    To use the components in the building alteration wizards, do the following:

  5. Click Demolition Object, New Building Object.
  6. Click Properties and define the parameters for the first layer of the demolition object and the new building object in one of the following ways:
  7. Select the demolition opening and the new building opening and click Apply.
  8. Open a selection rectangle so that the demolition opening and the new building opening in the first construction layer are fully bounded. Make sure that you do not include the openings in the second construction layer of the wall:

    The program selects these parts of the openings and displays the edges of the first construction layer in selection color:

  9. Click Apply.

    Allplan automatically creates demolition and new building objects of the correct geometry and height association in the first construction layer in the wall. In addition, these objects are automatically given the relevant format properties and attributes.

  10. Repeat steps 6 to 9 for more construction layers.

    Allplan automatically creates demolition and new building objects of the correct geometry and height association in the second construction layer in the wall. In addition, these objects are automatically given the relevant format properties and attributes.